Manifold and Dock Pump Mechanical Install
Timeline
5 months
Scope of Services
Front-End Planning
Detail Engineering & Design
Procurement
Fabrication
Construction
Key insights
  • Scope included vault piping installation in 4 separate manifold vaults and installation of piping to tie in the vaults
  • Installation of 3 vertical pumps and 3 horizontal pumps, underground pipe from main vault to the pumps, and above ground tie-in pipe to the ship dock pipe rack
  • +450 bolt ups, including many Twin Seal valves, +2,000LF of underground pipe, and 9,200LF of above ground pipe

This is just one of the many mechanical install projects we have performed. For more information on our full breadth of experience, reach out to our team today.

Introduction

These projects were part of our client's phase 1 plan for a new refined products terminal in Pasadena, Texas.

The Problem

H+M’s scope was only part of the overall plan to get the terminal completed and commissioned on time as ships had already been scheduled to unload and put the terminal in operation. H+M was under pressure to deliver the project.

Challenges

The project’s main challenges included the site conditions and terrain which made it very difficult to bring materials to the site, set up cranes, and execute the work. The schedule to complete was of concern and there were many other contractors to coordinate with.

Outcomes

H+M was able to complete both projects safely and on time for the client to receive their first ship at the terminal. Site conditions were mitigated as best as possible including bringing in mats to aid in the movement of equipment to perform the work inside of the vaults. An underground pipe installation plan, which included dewatering, was put in place and executed and UG pipe installed successfully. Coordinated with other contractors to plan work that was in the same area (SIMOPS).

"This was a challenging and exciting job for our team. We were confident we would be able to tackle it and deliver to our client."
Hugo McBride
Sr. Construction Manager - H+M Industrial EPC

Ready to work together?

We’d love to sit down with you and discuss your design/build, engineering and construction needs.
Robyn Hall
Sr. Marketing Manager
832-558-6212
To learn more about our unique approach to project execution, or to schedule a consultation, please give us a call or fill out the form below.
Success!
Your submission was successful and we will be in touch soon
Oops! Something went wrong while submitting the form.
View Next Project
Brownfield Custom Design Scrubber Installation